Construction
Update
December 8, 2008 (click
here for photos)
Just beat the weather…
Monday
December 8, 2008 brought the heavy equipment to Midwest Covenant
Home. Clairmont Construction began pouring the concrete for
our new Dining Room floor…and just in the nick of time.
As you all know, snow fell along with temperatures which could
have caused delays for the pour.
Sometimes
it is better to be lucky than talented!
The short-term
schedule for construction is framing of the exterior walls
for the rest of the week of December 8, 2008, followed by
the continuation of roofing for the new addition.

Click on the images below to enlarge.
|